TDOT Montgomery County Warfield Blvd Utilities – Clarksville, TN

TDOT Montgomery County Warfield Blvd Utilities – Clarksville, TN

Scope of work: Included the installation of 1,055 linear feet of 18” PVC and DIP, 10,496 linear feet of 16” DIP and HDD, 3,240 linear feet of 12” PVC and DIP, 226 linear feet of 8” DIP, 1,746 linear feet of 6” DIP, bores, manholes, PVC laterals, services, and site...
Ladd Park Interceptor Sewer – Franklin, TN

Ladd Park Interceptor Sewer – Franklin, TN

Scope of work: Included the installation of approximately 3,495 linear feet of 24” DIP gravity sewer, 2,360 linear feet of 18” PVC gravity sewer, 19 manholes, 10 check dams, by-pass pumping, and general sitework. Job...
West Park EQ Facility Phase 2 – Nashville, TN

West Park EQ Facility Phase 2 – Nashville, TN

Scope of work: Included the installation of EQ facility basin, which holds 21 million gallons of water. Over 140,000 tons of rock were removed, 9,000 cubic yards of concrete poured, and over 5,000 gallons of paint to complete the project. The EQ basin can be seen off...